When you try our part of Microsoft certification 70-178 exam practice questions and answers, you can make a choice to our ITCertKing. We will be 100% providing you convenience and guarantee. Remember that making you 100% pass Microsoft certification 70-178 exam is ITCertKing.
ITCertKing can not only achieve your dreams, but also provide you one year of free updates and after-sales service. The answers of ITCertKing's exercises is 100% correct and they can help you pass Microsoft certification 70-178 exam successfully. You can free download part of practice questions and answers of Microsoft certification 70-178 exam online as a try.
ITCertKing's practice questions and answers about the Microsoft certification 70-178 exam is developed by our expert team's wealth of knowledge and experience, and can fully meet the demand of Microsoft certification 70-178 exam's candidates. From related websites or books, you might also see some of the training materials, but ITCertKing's information about Microsoft certification 70-178 exam is the most comprehensive, and can give you the best protection. Candidates who participate in the Microsoft certification 70-178 exam should select exam practice questions and answers of ITCertKing, because ITCertKing is the best choice for you.
You feel tired when you are preparing hard for Microsoft 70-178 exam, do you know what other candidates are doing? Look at the candidates in IT certification exam around you. Why are they confident when you are nervous about the exam? Is your ability below theirs? Of course not. Have you wandered why other IT people can easily pass Microsoft 70-178 test? The answer is to use ITCertKing Microsoft 70-178 questions and answers which can help you sail through the exam with no mistakes. Don't believe it? Do you feel it is amazing? Have a try. You can confirm quality of the exam dumps by experiencing free demo. Hurry up and click ITCertKing.com.
Exam Code: 70-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2014-01-03
70-178 Free Demo Download: http://www.itcertking.com/70-178_exam.html
NO.1 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft 70-178 braindump 70-178 exam dumps
NO.2 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft demo 70-178 70-178
NO.3 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft 70-178 70-178 certification 70-178 certification training 70-178
NO.4 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft study guide 70-178 70-178
NO.5 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft dumps 70-178 70-178 70-178 practice test 70-178
NO.6 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft braindump 70-178 70-178 dumps
NO.7 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft 70-178 braindump 70-178 dumps 70-178 exam dumps
NO.8 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft 70-178 70-178
NO.9 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft exam simulations 70-178 70-178 exam prep 70-178
NO.10 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft 70-178 70-178
ITCertKing offer the latest SY0-301 exam material and high-quality LOT-951 pdf questions & answers. Our HP2-E59 VCE testing engine and 00M-654 study guide can help you pass the real exam. High-quality LOT-958 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.